Surface Technology

Athletic Flooring Contractor.

Georgetown University Athletic Center

Project:

Coat nine locker room floors

Location:

Washington, D.C.

Services:

Contract administration, project management

Size:

3,300 square feet

Duration:

2 weeks

Scope:

Surface Technology provided contract administration and project management and supplied materials to coat nine locker room floors at the new Georgetown University athletic center.

Highlights:

After an issue with the original subcontractor at the end of the job, Surface Technology was asked to complete the project and make up for lost time.

The project was challenging in that work was spread out across nine rooms and four floors. With only one elevator available, workers had to carry much of the material up the stairs.

Work was completed within budget several days ahead of schedule with no punch list.